The Margin Autopsy: How We Learned to Price Agency Work After Losing 18% on a 'Good' Project

Most agency projects don't fail loudly. They bleed quietly through unlogged hours, rework, and the senior engineer you borrowed for 'just a quick call'. Here's the autopsy template we use to stop it.

We delivered a project last year that everyone called a win. Client was happy, team was proud, case study went on the site. Then finance ran the final numbers and we were 18% under water on a fixed bid we thought had a 25% buffer. Nobody saw it coming because nobody was looking in the right place.

This is the autopsy we now run on every project above a certain size, and the pricing adjustments that came out of it. If you run an agency or a studio, you've probably lost margin the same way we did — the question is whether you can name exactly where.

Why 'we went over hours' is a useless answer

When a project loses money, the default post-mortem usually lands on one of three excuses: the client was difficult, the scope was fuzzy, or the team under-estimated. All three are sometimes true. None of them are actionable.

The problem with those answers is that they treat the project as one undifferentiated blob of effort. In reality, a 14-week engagement is dozens of distinct cost centres, and margin almost never leaks from all of them at once. It leaks from two or three specific places, and if you don't isolate them, you'll price the next project with the same hidden tax baked in.

So we stopped asking 'did we go over?' and started asking 'where, specifically, did each hour cost more than we sold it for?'

The autopsy template

We break every post-project review into seven buckets. For each bucket, we compare sold hours to actual hours, and more importantly, we compare the blended rate we sold against the blended rate we actually used. That second comparison is where most of the surprises live.

Here's the structure we use in a shared sheet:

Bucket                     Sold hrs   Actual hrs   Sold rate   Actual rate   Delta ($)
---------------------------------------------------------------------------------------
1. Discovery & shaping
2. Core build (planned)
3. Change requests
4. Rework (our fault)
5. Rework (client-driven)
6. Coordination overhead
7. Warranty & handover

The magic is in buckets 4, 5, and 6. Those are the ones nobody tracks in advance, and they're almost always where the money went.

How to actually populate it

You cannot do this honestly from memory. We now require two things during delivery:

  1. Every Jira ticket (or Linear, or whatever) carries a bucket tag. Engineers pick one when they log time. It takes four seconds and it's non-negotiable.
  2. Every meeting over 30 minutes gets logged against the project with attendees, even if it was 'quick'. That's bucket 6.

Without those two disciplines, your autopsy is fiction. With them, you can run the numbers in about an hour at project close.

What our 18% loss actually was

When we ran the autopsy on the project I mentioned, here's what came out. I'm rounding to protect the client but the shape is accurate.

  • Core build: 4% under budget. The team was great.
  • Change requests: billed and approved, slight positive margin. Fine.
  • Rework (our fault): about 6% of total budget. A data model decision we made in week three cost us a fortnight of refactoring in week nine.
  • Rework (client-driven): about 5%. The client's head of marketing joined in week seven and 'wanted to see options' on three flows we'd already signed off.
  • Coordination overhead: about 9%. Four stakeholders on the client side, two of whom disagreed with each other, and a weekly steering call that always ran long.

The core build was fine. The build is almost always fine. The margin was eaten by coordination and two flavours of rework, and we had sold the project as if those costs were zero.

The pricing changes that came out of it

Once you can see where money actually leaks, you can price for it. We made four concrete changes.

1. Coordination is a line item now

We used to bundle PM and account management into a vague overhead percentage. Now we quote it explicitly, sized by the number of client-side stakeholders. One or two stakeholders: standard rate. Three to five: add 15%. Six or more: we either add 25% or decline the project. Clients push back on this less than you'd think, because the line item makes the cost of their internal politics visible to them, not just to us.

2. A rework allowance, named out loud

Every fixed bid now includes a 'revision budget' — a named pool of hours for client-driven changes that fall short of a formal change request. When it's gone, it's gone, and the next revision triggers a CR. This moved a huge amount of ambiguity out of the grey zone where margin used to die quietly.

3. Architecture decisions get a second pair of eyes

The 6% self-inflicted rework on that project came from one bad early call made by a strong engineer working alone. We now require every project above a threshold to have a second senior engineer review the core architectural decisions in week one or two. It costs us maybe 8 hours. It has already saved us multiples of that on two projects since.

If you want the longer version of how we structure that, we've written about our approach to paid architecture work before.

4. Fixed bid only where the shape is known

We used to default to fixed bids because clients asked for them. Now we default to T&M with a cap for anything where the data model, integrations, or user flows aren't fully specified. Fixed bids are reserved for work where we've either done something very similar before, or where discovery has produced artefacts detailed enough that a competent engineer could estimate them to within 15%.

This cost us one deal in the last year. It saved us from at least two projects that would have looked like the 18% loss.

The thing nobody wants to hear

Here's the uncomfortable part. Most agencies that are 'doing fine' are actually running at 5–10% net margins and don't realise it, because their utilisation is masked by a few projects that over-performed and a founder who isn't paying themselves properly.

In our experience, once you start running honest autopsies, the first three or four come back ugly. You'll find a project you were proud of that lost money. You'll find a client you love who is unprofitable. You'll find a senior engineer whose 'quick help' across three projects adds up to a full week a month of uncosted time.

That's not a reason to stop looking. It's the reason to start. You cannot fix margin you cannot see.

A note on what this is not

This template is not a performance review tool. The moment engineers think bucket tags will be used to rank them, the data goes to zero quality. We've been explicit internally: autopsies are about pricing and process, never about individuals. The engineer who made the bad data model call on that project got a bonus that year, because the lesson belonged to the company, not to them.

If you can't make that commitment and keep it, don't start. Bad data is worse than no data.

Where we'd start

If you want to try this on your next project, do the minimum version:

  • Add the seven buckets to your time tracker this week. Don't rebuild anything else.
  • On your next project kickoff, write down the assumed split across those buckets. This is your implicit pricing model, made visible.
  • At project close, compare assumed to actual. Don't try to fix anything yet. Just look.

After three projects, you'll see a pattern. After five, you'll know exactly which two buckets are eating your margin, and you can start pricing them like adults. That's the whole game.

If you'd rather talk through how this maps to your specific service mix, our engineering services page has the shape of the work we do and how we scope it.

#pricing#agency#project management#founders